Regulation updates
Supported housing licensing: what the draft regulations require, and how to respond by 10 December
By M Saeed, Founder, Evidix
In short
Under draft regulations published for consultation on 15 October 2026, councils across England would license the supported exempt accommodation in their areas. A licence lasts five years, is personal to the licence holder, and carries conditions, including a needs assessment for each resident within 4 weeks of moving in and meeting the National Supported Housing Standards. Councils could require documents, issue warning and improvement notices, and fine up to £7,000. The consultation closes on 10 December 2026; no start date has been set.
On 15 October 2026 the government published draft regulations for licensing supported housing in England, with an eight-week consultation that closes on 10 December 2026. They are made under the Supported Housing (Regulatory Oversight) Act 2023, and they would give councils the power to license the supported exempt accommodation in their areas.
This guide sets out what the draft says: what counts as supported housing, who can apply for an exemption, what a licence is, the conditions it carries, and what a council could ask for. Everything below is quoted from the draft regulations or the consultation document. Nothing is law yet.
Where does licensing stand?
The government consulted on the design of the regime in 2025. Its response, published in April 2026, “confirmed the government’s intention to proceed with a locally led licensing regime in all local authority areas to give councils the enforcement powers that they need to manage the supported housing in their area.”
The draft regulations are the next step. The consultation says: “Subject to parliamentary approval, the government intends to implement the licensing regime, supported by guidance for local authorities and providers.” It also says the regulations “would not all come into force at the same time. In particular, the rules on offences and banning orders would start later than the other provisions.”
No start date has been published.
What counts as supported housing?
The draft defines “supported housing” as supported exempt accommodation, which section 12(1) of the 2023 Act defines as:
“(a) accommodation within subsection (2), (b) managed properties in England, (c) refuges in England, or (d) local authority hostels in England.”
Subsection (2) includes accommodation in England “provided by— (i) a non-metropolitan county council in England, (ii) a housing association, (iii) a registered charity, or (iv) a voluntary organisation, where that body, or a person acting on its behalf, also provides a person resident in the accommodation with care, support or supervision.” Section 12 also defines managed properties, refuges and local authority hostels; read it in full to see where your homes fall.
The supported exempt accommodation that licensing covers is not on the new landlord database. The government’s guidance for landlords says: “You do not need to register if you operate a tenancy that is included in the meaning of supported exempt accommodation set out in Section 12 of the Supported Housing (Regulatory Oversight) Act 2023.”
Who can apply for an exemption?
The draft lets certain categories of supported housing apply for an exemption. The consultation lists them:
- some low-cost older people’s provision
- local authority owned provision
- domestic abuse refuges commissioned by local authorities
- certain criminal justice accommodation commissioned by the Ministry of Justice
- specific provision for younger people where Ofsted regulates some of the bedspaces and is commissioned by local authorities
- almshouses
An exemption is not automatic. The consultation says these types of housing “will still need to apply for an exemption from the licensing authority, and the licensing authority needs to approve that exemption.”
Registered providers do not appear on the list as a category of their own.
What is a licence?
The consultation says: “All licences should list the licence holder and properties to be covered by the licence, include mandatory conditions (set out in Schedule 3) and specify a five-year duration. The licensee must be a fit and proper person and must be the most appropriate person to hold the licence.”
A licence is personal to the licence holder. It can only change hands through a variation application to the council, and the licence holder, and where relevant its directors or partners, must meet the fit and proper person requirements at all times.
Who must hold the licence?
The government's response to the 2025 consultation says:
“The Act sets out that a supported housing licence holder must be the person ‘managing or in control of’ the supported exempt accommodation. Depending on the exact circumstances there may be more than one person who could be the licence holder, for example a head landlord and a managing agent. The government would expect the organisations to agree between them who is the appropriate person to hold the licence, having regard to guidance and any relevant case law.”
If you lease homes from landlords, or run homes for a registered provider, that conversation is worth having before your council's scheme opens.
What happens to Housing Benefit?
Licensing and Housing Benefit are being tied together.
- The same homes. The consultation says the draft regulations' scope “mirrors the definition of specified accommodation in Housing Benefit regulations.”
- Entitlement linked to the licence. The government response says the government “will amend Housing Benefit regulations to link the new licensing regime in England to Housing Benefit entitlement.”
- Revocation is passed on. When a licence is revoked, “The licensing authority must also inform the relevant Housing Benefit team of the revocation.”
How entitlement will be linked in practice will be set out when those Housing Benefit regulations are amended.
What conditions would a licence carry?
Schedule 3 to the draft sets out the mandatory conditions under these headings:
| Heading | Paragraphs | What they cover |
|---|---|---|
| Licence holder | 1–4 | the licence is personal; the holder changes only by a variation application; the holder, and an organisation's directors or partners, meet the fit and proper requirements at all times |
| Other persons | 5 | the named service manager changes only by variation; an organisation keeps a nominated individual |
| Specified supported housing | 6–7 | the licence covers only the housing named in it; its nature or type changes only by variation |
| Other significant changes | 8–9 | new directors, partners or controllers, or a new service manager, need a variation |
| Notifiable changes | 10 | a change of nominated individual is notified in writing within 14 days |
| Compliance with standards | 11 | any Housing Standard and the national standards under section 3 of the 2023 Act |
| Standard of accommodation | 12–13 | for housing that is not social housing of a registered provider, no enforcement action on a category 1 hazard; and the housing is “(a) safe; (b) well maintained including regular cleaning of communal areas; (c) accessible for its intended residents” |
| Needs assessments | 14–15 | an assessment for each resident within 4 weeks of moving in, by a suitably skilled person |
| Quality of care provided | 16–17 | a care provider registered under the Health and Social Care Act 2008; other support or supervision meets the national standards |
| Fees | 18 | any annual fee paid within 14 days of notice |
Two conditions are worth reading word for word.
Needs assessments. “The licence holder must ensure an assessment of the needs of each resident of the supported housing is carried out no later than 4 weeks after the date on which the person starts living in the housing.” (Schedule 3, paragraph 14.) The consultation adds that “Assessments must be carried out by someone appropriately skilled and meet the National Supported Housing Standards.”
The National Supported Housing Standards. “The licence holder must ensure the supported housing meets the National Supported Housing Standards (NSHS). Commissioned services do not need to meet this condition but must be commissioned in line with the NSHS.”
What could a council ask for?
The draft gives councils three ways to ask for information and act on it.
Documents. Under regulation 24(1), “the licensing authority may give a notice to a licence holder requiring them, at a time and place specified, to produce any document”, including any document “in their custody or under their control”.
Information, when it suspects a breach. Under regulation 24(4)(a), it may give “a notice (“information notice”) to the licence holder requiring them to provide any information the authority consider relevant”.
Warning and improvement notices, and fines. The consultation says a warning notice must “specify a deadline for improvement (up to three months)”. If the improvements are not agreed or not made, the council may issue an improvement notice, and “The licensing authority can impose a fine of up to £7,000 alongside issuing an improvement notice.”
The draft also includes a power of entry: “Licence holders and any occupiers must be given at least 24 hours’ advance notice.” A licence “must be revoked if the licence holder no longer meets the requirements of the fit and proper person test”, and councils “would have to publish the names and addresses of each licence holder in the district, along with the date their licence was granted”, though not the locations of the housing.
What about HMOs?
Some supported housing is also a licensed house in multiple occupation. The consultation says the draft regulations “provide transitional protection for HMO licence holders.”
How do you respond by 10 December?
The consultation runs for eight weeks from 15 October 2026, so it closes on 10 December 2026. You respond through the online survey linked from the consultation page, which also gives an email address for enquiries.
If you respond, evidence from your own records carries more weight than opinion: for example, how long needs assessments take after a resident moves in today.
What can a provider do now?
Nothing here is law yet. But every condition above is one a council would check against records, so the useful preparation is the same whatever the final text says:
- For each resident, the move-in date and the date of their needs assessment, side by side, so a gap over four weeks is visible now rather than at inspection.
- For each property, its certificates and repairs with dates, so “safe and suitable” can be shown, not asserted.
- For the organisation, the documents behind the fit and proper person test, for the licence holder, directors or partners, and the service manager.
- A record of who changed what, and when, because a council can ask for any document in your custody or under your control.
If you also manage homes let on a tenancy, the landlord database and the Awaab’s Law consultation are the other two changes to plan for this winter.
Get the Exempt accommodation: the evidence a Housing Benefit review will ask for (PDF)
A per-scheme and per-resident checklist of what a council checks on a supported or exempt accommodation claim, with what is in force and what is only proposed.
Try Evidix free
Evidix keeps the deadlines, the records and the evidence behind them in one place. 14-day free trial on every plan; plans from £30 a month.
Questions
- What is the Supported Housing (Regulatory Oversight) Act 2023?
- It is the Act that set up a new framework for regulating supported housing in England. The government says it responded to “significant and longstanding concerns about the quality, oversight and value for money of some supported housing provision, particularly within the exempt accommodation sector”. The licensing regime in these draft regulations is made under it.
- What is classed as supported housing?
- In the draft regulations, supported housing means supported exempt accommodation as defined in section 12 of the Supported Housing (Regulatory Oversight) Act 2023: “(a) accommodation within subsection (2), (b) managed properties in England, (c) refuges in England, or (d) local authority hostels in England.”
- Who must hold a supported housing licence?
- The government response says the licence holder “must be the person ‘managing or in control of’ the supported exempt accommodation”, and that “there may be more than one person who could be the licence holder, for example a head landlord and a managing agent.” The organisations are expected to agree between them who holds it.
- When will supported housing licensing start?
- No date has been set. The consultation says “Subject to parliamentary approval, the government intends to implement the licensing regime”, and that the rules on offences and banning orders “would start later than the other provisions”. The consultation itself closes on 10 December 2026.
- Do registered providers need a supported housing licence?
- The draft exemptions do not include registered providers as such. The categories that can apply for an exemption are low-cost older people’s provision, local authority owned provision, domestic abuse refuges commissioned by local authorities, certain Ministry of Justice criminal justice accommodation, some Ofsted-linked provision for younger people commissioned by local authorities, and almshouses. Even those must apply for the exemption and have it approved.
- Does supported exempt accommodation have to register on the landlord database?
- No. The government’s guidance for landlords says: “You do not need to register if you operate a tenancy that is included in the meaning of supported exempt accommodation set out in Section 12 of the Supported Housing (Regulatory Oversight) Act 2023.”
- What is the fine for breaching a licence condition?
- Under the proposals, a council that issues an improvement notice “can impose a fine of up to £7,000 alongside issuing an improvement notice”. A licence can also be revoked, for example if the licence holder no longer meets the fit and proper person test.
Sources
- Draft Supported Housing (Licensing) (England) Regulations 2027
- MHCLG: Supported housing licensing regime, consultation on draft regulations (15 October 2026)
- MHCLG: Supported housing regulation consultation, government response (April 2026)
- Supported Housing (Regulatory Oversight) Act 2023, section 12
- MHCLG: Register your rental property service, guidance for landlords
Related
- Temporary accommodation inspection checklist: what the law and the Code of Guidance require
A temporary accommodation inspection checklist for England, built from the Housing Act 1996, the Homelessness Code of Guidance and the 2012 Suitability Order: hazards, gas and electrical safety, alarms, fire, HMO licensing, space and B&B limits, with a free printable checklist.
- What is supported exempt accommodation? The definition, Housing Benefit, and what licensing changes
Supported exempt accommodation in England, for the organisations that provide and manage it: the definition in the 2023 Act and the Housing Benefit rules, the four kinds of specified accommodation, why rent is paid through Housing Benefit rather than Universal Credit, and what licensing will change.
- Awaab's Law Phase 2: the new hazard groups, with examples and timescales
From 30 November 2026, Awaab's Law covers significant hazards from excess cold and heat, falls, structural collapse, fire and explosions, electricity and domestic hygiene. What each group covers, how to tell emergency from significant, and what stays out.